8.03.404x RSB & MRSB - Move Job

Just as an FYI to those that use RSB and MRSB...

By default, Epicor has changed the base logic as this checkbox is set
by default as TRUE and their only recommendation is to do a BPM to
default to FALSE. Additionally, if you have APS and use
Capabilities, be aware that by default it will remove the Capability
ID and related Resource Group ID when you move a job in MRSB.
However, if you move a job in the RSB, then checkbox is grayed out
and defaulted to TRUE but does not remove the Cap ID and RG ID. So
the logic between the two are not even consistant.

Oh...and this new feature/enhancement is not documented in the SP or
Patch Change lists.

Update Job Operation Detail
Check this box to update the resource set in the Job Operation Detail
with the resource specified here, if the number of scheduling blocks
is 1. This box is useful when the original resource on the job needs
to be changed, and the information should be sent to the job record.

This box is enabled only when the number of scheduling blocks is 1.

If the costing rates are different between the new resource and the
existing one, the Override Rates checkbox will be checked and the
existing rates will be retained. In other words, this checkbox does
not set new rates for production labor or burden.