What is the best way to account for the time getting parts through Receiving Inspection when Inspection Required is marked on a part to reflect in a jobs schedule. Production Prep Buffer, Kit Time, Receive Time?
Thanks!
What is the best way to account for the time getting parts through Receiving Inspection when Inspection Required is marked on a part to reflect in a jobs schedule. Production Prep Buffer, Kit Time, Receive Time?
Thanks!
I would use receive time, but that could be too much. You can only enter days in the field, so if inspections that take less than a day, it will push the schedule out.