Then you end up with 6 'extra' good pieces in stock (unless you want to articially scrap them just so the loss is rolled into job cost and you end up with no inventory to carry).
Wouldn't you be better off focusing on how to foolproof your processes so you don't incur the scrap (versus trying to figure out a way to complicate your planning and system processes to compensate for the scrap)?
Who do you want to be? General Motors, Chrysler, Ford (MRP II and heading towards bankruptcy) or Toyota, Honda, Nissan, etc., (reliable value-added Lean processes, simple ERP processes as a result - and profitable).
More complex computer models aren't the goal, they are a non-value added cost.
Rob
Wouldn't you be better off focusing on how to foolproof your processes so you don't incur the scrap (versus trying to figure out a way to complicate your planning and system processes to compensate for the scrap)?
Who do you want to be? General Motors, Chrysler, Ford (MRP II and heading towards bankruptcy) or Toyota, Honda, Nissan, etc., (reliable value-added Lean processes, simple ERP processes as a result - and profitable).
More complex computer models aren't the goal, they are a non-value added cost.
Rob
--- On Wed, 11/19/08, Ari Footlik <ari@...> wrote:
From: Ari Footlik <ari@...>
Subject: RE: [Vantage] Re: Backward Scheduling to Include Extra Parts
To: vantage@yahoogroups.com
Date: Wednesday, November 19, 2008, 1:39 PM
Thanks. I was considering this, but my question in this case is:
What happens if we end up making 6 good pcs and none of the extra 6 get
scrapped?
--Ari
____________ _________ _________ __
From: vantage@yahoogroups .com [mailto:vantage@yahoogroups .com] On Behalf
Of gsc1161
Sent: Wednesday, November 19, 2008 12:31 PM
To: vantage@yahoogroups .com
Subject: [Vantage] Re: Backward Scheduling to Include Extra Parts
You can set a scrap factor at each component on the assemblies
method, so that MRP see "extra" demand for the component. The scrap
factor can be a fixed quantity, or a % of the assembly quantity.
--- In vantage@yahoogroups .com <mailto:vantage% 40yahoogroups. com> , "Ari
Footlik" <ari@...> wrote:
>
> I just realized that there is an opportunity to greatly improve our
> scheduling of jobs. Specifically, what I realized is that for
every job
> we always plan to make (and actually make) extra pieces, but we do
this
> without informing Vantage we're going to do it.
>
> For example, we have an order for 50 pcs and we know we're going to
make
> 56 pieces (just-in-case) , but the order in Vantage tied to the job
is
> for only those original 50 pcs. Therefore, the backward scheduling
is
> done only for 50 pcs, and there is no allowance in the schedule for
the
> extra pieces we *know* we're going to run. Even in the best case,
then,
> where we hit the target minutes/piece, we'll still blow the schedule
> because we took the time to make 6 extra pieces!
>
> So, what is the best way to include these extra pieces in the
> scheduling? Do we do add a "Make to Stock" demand for the job (if
we
> scrap some of the 6, won't we get an "under-quantity" warning)? Or
do
> we add 6 pcs of scrap to each operation (would we have to add it to
> every op, or just the first and it'd carry through)? Is there
another
> option I'm not seeing?
>
> Thanks!
> --Ari
>
[Non-text portions of this message have been removed]