BAM - Progress Help

Yes, we would like for it to alert us for only when Op 9000 is complete
on any job with a listing of which job the op 9000 is completed on.



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Bill Jackson
Sent: Tuesday, September 18, 2007 6:50 AM
To: vantage@yahoogroups.com
Subject: Re: [Vantage] BAM - Progress Help



DO you mean filter to OpComplete = Yes and OpSeq( or OPCode, etc.) =
'9000' ?
Are you retrieving the JobNUm based on those 2 conditions?

"Moore, Jim (Anniston)" <jmoore@...-ots.com
<mailto:jmoore%40dri.gd-ots.com> > wrote:
I need to know how to setup a BAM so that when an operation is complete
(9000 in our case) that an email will be sent to an individual so she
will know it is complete and for what job that op is completed on.

I know how to set the BAM up, just need the code for the external
program to filter it to only OP 9000 and the name of the job.

I've looked thru the archives and in the group files, but did not see
anything too close I could edit.
I'm sure this is a simple Progress statement, but if someone could get
me going I would appreciate it.

Thanks,

Jim Moore








[Non-text portions of this message have been removed]
I need to know how to setup a BAM so that when an operation is complete
(9000 in our case) that an email will be sent to an individual so she
will know it is complete and for what job that op is completed on.

I know how to set the BAM up, just need the code for the external
program to filter it to only OP 9000 and the name of the job.

I've looked thru the archives and in the group files, but did not see
anything too close I could edit.
I'm sure this is a simple Progress statement, but if someone could get
me going I would appreciate it.

Thanks,

Jim Moore
------------------------------------------------------------------------
------------------------------
"This email message is for the sole use of the intended
recipient(s) and may contain proprietary and/or confidential
information for which such intended recipients(s) may have
an obligation to treat as proprietary. Any unauthorized review,
use, disclosure, or distribution is strictly prohibited. If you are
not the intended recipient, please contact sender by reply
email and destroy all copies of this e-mail."
------------------------------------------------------------------------
-----




[Non-text portions of this message have been removed]
IF JobOper.OpSeq <> 9000 THEN DO:
RETURN "Cancel Send".
END.
ASSIGN Email-To = "email address".
ASSIGN Email-Subject = JobOper.JobNum + " has been completed".
ASSIGN Email-Text = "Job No. " + JobOper.JobNum + " has been completed.".


-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com]On Behalf Of Moore, Jim (Anniston)
Sent: Monday, September 17, 2007 4:30 PM
To: vantage@yahoogroups.com
Subject: [Vantage] BAM - Progress Help



I need to know how to setup a BAM so that when an operation is complete
(9000 in our case) that an email will be sent to an individual so she
will know it is complete and for what job that op is completed on.

I know how to set the BAM up, just need the code for the external
program to filter it to only OP 9000 and the name of the job.

I've looked thru the archives and in the group files, but did not see
anything too close I could edit.
I'm sure this is a simple Progress statement, but if someone could get
me going I would appreciate it.

Thanks,

Jim Moore
----------------------------------------------------------
------------------------------
"This email message is for the sole use of the intended
recipient(s) and may contain proprietary and/or confidential
information for which such intended recipients(s) may have
an obligation to treat as proprietary. Any unauthorized review,
use, disclosure, or distribution is strictly prohibited. If you are
not the intended recipient, please contact sender by reply
email and destroy all copies of this e-mail."
----------------------------------------------------------
-----

[Non-text portions of this message have been removed]







[Non-text portions of this message have been removed]
DO you mean filter to OpComplete = Yes and OpSeq( or OPCode, etc.) = '9000' ?
Are you retrieving the JobNUm based on those 2 conditions?

"Moore, Jim (Anniston)" <jmoore@...-ots.com> wrote:
I need to know how to setup a BAM so that when an operation is complete
(9000 in our case) that an email will be sent to an individual so she
will know it is complete and for what job that op is completed on.

I know how to set the BAM up, just need the code for the external
program to filter it to only OP 9000 and the name of the job.

I've looked thru the archives and in the group files, but did not see
anything too close I could edit.
I'm sure this is a simple Progress statement, but if someone could get
me going I would appreciate it.

Thanks,

Jim Moore
----------------------------------------------------------
------------------------------
"This email message is for the sole use of the intended
recipient(s) and may contain proprietary and/or confidential
information for which such intended recipients(s) may have
an obligation to treat as proprietary. Any unauthorized review,
use, disclosure, or distribution is strictly prohibited. If you are
not the intended recipient, please contact sender by reply
email and destroy all copies of this e-mail."
----------------------------------------------------------
-----

[Non-text portions of this message have been removed]






---------------------------------
Yahoo! oneSearch: Finally, mobile search that gives answers, not web links.

[Non-text portions of this message have been removed]