in Pharmaceutical industry how we can assign fixed batch size such as 10KG, 20KG,50KG under part revision level not under part , and let MRP to open job with specific revision without any human input.
In current , the lot min/max/ multiple not matched customer requirements.
customizing MRP is not really an option, BUT, I have seen BPMs written that “modify the results” of MRP… for example, you could have a BPM that would fire when a new unfirm job is created by MRP… the BPM would analyze the job, and why it is made (who the customer is?) and then modify the results, such as the quantity, dates, etc.
We add three fields under revision level , this help pharmaceutical industry to determine three batch size , after run MRP we using Split job functionality 'using code ’ to split jobs based on batch size