Calendar and scheduling

so if queue time in Vantage 6 was 24 hours the queue time in Vantage 8 will need to be 72? (because Vantage 6 was based on 8 hours a day 5 days a week and Vantage 8 is 24/7)
Â
also if i had an outside processing lead time of 15 m-days what happens to the lead time in Vantage 8?

--- On Fri, 1/9/09, Mark Wagner <mjfw2003@...> wrote:

From: Mark Wagner <mjfw2003@...>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups.com
Date: Friday, January 9, 2009, 9:47 PM






Tara, we tried and as I remember (it was awhile ago) queue times without APS are calendar based and can only be scheduled in 24 hour increments
--- On Fri, 1/9/09, Tara McCrorey <mccroreytara@ yahoo.com> wrote:

From: Tara McCrorey <mccroreytara@ yahoo.com>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups .com
Date: Friday, January 9, 2009, 2:35 PM

Queue times inbetween operations on the same job is what i am looking for.

--- On Fri, 1/9/09, vantage <vantage@rmgfelm. com> wrote:

From: vantage <vantage@rmgfelm. com>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups .com
Date: Friday, January 9, 2009, 7:00 PM

You will have to confirm this, but I think they changed queue times to only
work between routing in the same job. If you want queue time between jobs,
ie. first operation, you have to use the kit time or production prep buffer.

Steve

-----Original Message-----
From: mccroreytara [mailto:mccroreytar a@ yahoo.com]
Sent: January 09, 2009 12:38 PM
To: vantage@yahoogroups .com
Subject: [Vantage] calendar and scheduling

after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?

[Non-text portions of this message have been removed]

[Non-text portions of this message have been removed]

[Non-text portions of this message have been removed]


















[Non-text portions of this message have been removed]
after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?
Queue times are scheduled off a 24 hour/ 7 day week even if your shops
hours are different. This makes sense as it allows the user to change
the shop calendar without having to recalculate the queue times on
operations. The problem is that 48 hours of queue time may not result
in 2 working days depending on when the job is scheduled and if the
weekend comes into play.



Regards,





Andrew Best

Kice Industries, Inc.

P(316)744-7151

F(316)295-2412



From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of mccroreytara
Sent: Friday, January 09, 2009 12:38 PM
To: vantage@yahoogroups.com
Subject: [Vantage] calendar and scheduling



after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?





[Non-text portions of this message have been removed]
You will have to confirm this, but I think they changed queue times to only
work between routing in the same job. If you want queue time between jobs,
ie. first operation, you have to use the kit time or production prep buffer.

Steve

-----Original Message-----
From: mccroreytara [mailto:mccroreytara@...]
Sent: January 09, 2009 12:38 PM
To: vantage@yahoogroups.com
Subject: [Vantage] calendar and scheduling



after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?







[Non-text portions of this message have been removed]
Queue times inbetween operations on the same job is what i am looking for.

--- On Fri, 1/9/09, vantage <vantage@...> wrote:

From: vantage <vantage@...>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups.com
Date: Friday, January 9, 2009, 7:00 PM






You will have to confirm this, but I think they changed queue times to only
work between routing in the same job. If you want queue time between jobs,
ie. first operation, you have to use the kit time or production prep buffer.

Steve

-----Original Message-----
From: mccroreytara [mailto:mccroreytara@ yahoo.com]
Sent: January 09, 2009 12:38 PM
To: vantage@yahoogroups .com
Subject: [Vantage] calendar and scheduling

after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?

[Non-text portions of this message have been removed]


















[Non-text portions of this message have been removed]
I had this same issue. Look at the Production Calendar Hours. You probably have them 1-8 or if you run a 16 hour day, 1-16. The numbers actually represent the Hour of the Day. so 1 represents 1 am and so on.
Â
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
Â

--- On Fri, 1/9/09, mccroreytara <mccroreytara@...> wrote:

From: mccroreytara <mccroreytara@...>
Subject: [Vantage] calendar and scheduling
To: vantage@yahoogroups.com
Date: Friday, January 9, 2009, 12:38 PM






after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?


















[Non-text portions of this message have been removed]
so the help menu tells us to set the default hours to what our shop runs. tech support and the consultant told us to enter 24 as the default hours and chose what hours we would be running in the shop. i tried both ways and it didnt change the queue time inbetween operations on the same job.
Â
Tara McCrorey
Production Control
Damar Machine

--- On Fri, 1/9/09, Jonathan Lang <lsbestinc@...> wrote:

From: Jonathan Lang <lsbestinc@...>
Subject: Re: [Vantage] calendar and scheduling
To: vantage@yahoogroups.com
Date: Friday, January 9, 2009, 7:50 PM






I had this same issue. Look at the Production Calendar Hours. You probably have them 1-8 or if you run a 16 hour day, 1-16. The numbers actually represent the Hour of the Day. so 1 represents 1 am and so on.
Â
Jonathan LangÂ
Oil Rite Corporation
Sr. Network Administrator
Ph: (920) 682-6173 Ext: 126
Fax: (920) 682-7699
Â

--- On Fri, 1/9/09, mccroreytara <mccroreytara@ yahoo.com> wrote:

From: mccroreytara <mccroreytara@ yahoo.com>
Subject: [Vantage] calendar and scheduling
To: vantage@yahoogroups .com
Date: Friday, January 9, 2009, 12:38 PM

after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?

[Non-text portions of this message have been removed]


















[Non-text portions of this message have been removed]
Tara, we tried and as I remember (it was awhile ago) queue times without APS are calendar based and can only be scheduled in 24 hour increments
--- On Fri, 1/9/09, Tara McCrorey <mccroreytara@...> wrote:

From: Tara McCrorey <mccroreytara@...>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups.com
Date: Friday, January 9, 2009, 2:35 PM






Queue times inbetween operations on the same job is what i am looking for.

--- On Fri, 1/9/09, vantage <vantage@rmgfelm. com> wrote:

From: vantage <vantage@rmgfelm. com>
Subject: RE: [Vantage] calendar and scheduling
To: vantage@yahoogroups .com
Date: Friday, January 9, 2009, 7:00 PM

You will have to confirm this, but I think they changed queue times to only
work between routing in the same job. If you want queue time between jobs,
ie. first operation, you have to use the kit time or production prep buffer.

Steve

-----Original Message-----
From: mccroreytara [mailto:mccroreytar a@ yahoo.com]
Sent: January 09, 2009 12:38 PM
To: vantage@yahoogroups .com
Subject: [Vantage] calendar and scheduling

after converting from 6 to 8.03.406, we ran global rescheduling. all
the queue hours converted over but the schuedule of the job is
inaccurate. does anyone know what calendar 8 recognizes, is it
calendar hours or manufacturing hours? if it is calendar hours, do the
queue times need to be increased?