You need to tell MRP how you want it to create the jobs.
I am on 8.03.409 and in Engineering, Set Up, Part, Plant Tab there is an MRP Planning box top center. You can set a minimum quantity, and/or a multiple. If you set the Days of Supply MRP will find the first requirement then look out that number of days and combine all requirements in one job (and based on mins and multiples, if you set it.)
Georgia
--- In vantage@yahoogroups.com, "gabelebron07" <gabe.lebron@...> wrote:
>
> MRP creates internal fab jobs based on needs for other parts. Great, and it creates different jobs for the same part bases on different dates of need.
>
> Its more economical for us to build all at the same time rather than in 3 or 4 different jobs I know its easy to spilt a job, can you combine jobs or Delete others and change qty on one? What's the best way to accomplish this?
>
MRP creates internal fab jobs based on needs for other parts. Great, and it creates different jobs for the same part bases on different dates of need.

Its more economical for us to build all at the same time rather than in 3 or 4 different jobs I know its easy to spilt a job, can you combine jobs or Delete others and change qty on one? What's the best way to accomplish this?