I am working on setting up concurrent capacity on our TEST system.
we backwards schedule and we do rotational molding with multiple tools on two sides of an an arm.
I feel that I am half way there, but confused on the Resource Concurrent Capacity field versus the Part method and Job Entry Concurrent Capacity fields.
the tech guide is not very detailed for this area.
Is there a hierarchy for this entry at these three similar locations? Does anyone know?
Brad,
The best I have ever been able to tell is that the Resource Concurrent Capacity is the Max Concurrent capacity for the Resource.
Part Method should be the Default for the Jobs but it does not have to match the Concurrent capacity of the resource, it’s just the capacity that by default you need from the resource.
The Job can be changed as needed if that particular job run to fit the actual schedule needs.