Constrained Material for Manufactured Parts

Hello,

Hows constrained material for manufactured parts work? I have a Job A that is being fed by Job B for lets Call it Part A, Part A is constrained and its a manufactured part, so the purchasing lead time is 0. Job A is scheduled to start before Job B but Job A needs Job B to finish first.

The demand for Job B is make to stock because we make extras of these to put into stock before Job A is needed.

I did notice that when I make Job B make to job that it schedlues correctly.

Is it possible for manufactured parts that are constrained to look at Jobs that are make to stock and use that for scheduling or does the job need to be make to job.