No, you can't move or copy between checked out part numbers in workbench in
any Vantage version up to and including 8.0
I wish there was...It would be great if workbench had the same
functionality in that regard as the quoting module.
Usually, if I know I'm going to be setting up a bunch of parts that are
similar, or if it is really complex and I'm not sure exactly what I'm going
to do yet, I'll build all the methods in a quote, where I do have all the
copy features, then suck the details into workbench. Much faster than
loading everything manually in workbench and discovering you made a mistake
and have to rebuild it...
Amy O'Malley
Manufacturing Process Engineer
Synovis IS
omaLL004 @ umn.edu
any Vantage version up to and including 8.0
I wish there was...It would be great if workbench had the same
functionality in that regard as the quoting module.
Usually, if I know I'm going to be setting up a bunch of parts that are
similar, or if it is really complex and I'm not sure exactly what I'm going
to do yet, I'll build all the methods in a quote, where I do have all the
copy features, then suck the details into workbench. Much faster than
loading everything manually in workbench and discovering you made a mistake
and have to rebuild it...
Amy O'Malley
Manufacturing Process Engineer
Synovis IS
omaLL004 @ umn.edu
On Apr 27 2006, Jasper Recto wrote:
> Is it possible to copy an operation from one part number to another in
> the engineering workbench?
>
> We have a part and it has 3 operations. It is a subassembly to a top
> level part.
>
> What we want to do is take the last operation and move it to the first
> operation of the top level part number. We want all relative information
> and comments to go along with it.
>
>Is this possible?
>
>Thanks,