Cost Adjustment

Sometimes you can get a one off fix for the problem.



Steve



-----Original Message-----
From: Karl Dash [mailto:dashkarl@...]
Sent: November 07, 2008 10:22 AM
To: Vantage Group
Subject: [Vantage] Cost Adjustment



I patched our production Progress database to 406 and now find that the Cost
Adjustment program does not work as before. Using the grid to make multiple
entries (part number, cost, reason code), it burps after the first entry
claiming a bad reason code but lets you click on OK and then proceeds to the
next one, and so on. Our CFO doesn't consider this an acceptable solution
and the nice people at Epicor say that a fix will be available in 407 due
out the end of December. Has this problem been encountered already by anyone
else and an alternate solution derived? We don't have Service Connect, so
that is out of the question. Any suggestions?

Thanks as always,
-Karl

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]
I patched our production Progress database to 406 and now find that the Cost Adjustment program does not work as before. Using the grid to make multiple entries (part number, cost, reason code), it burps after the first entry claiming a bad reason code but lets you click on OK and then proceeds to the next one, and so on. Our CFO doesn't consider this an acceptable solution and the nice people at Epicor say that a fix will be available in 407 due out the end of December. Has this problem been encountered already by anyone else and an alternate solution derived? We don't have Service Connect, so that is out of the question. Any suggestions?
Â
Thanks as always,
-Karl




[Non-text portions of this message have been removed]
The problem was in 405a and at that time I was told that it would be fixed in 406. I haven't tried it yet in 406, but it sounds like it might be a little better. In 405a, you couldn't paste insert more then 2 or 3 before it would stop altogether.




________________________________
From: Karl Dash <dashkarl@...>
To: Vantage Group <vantage@yahoogroups.com>
Sent: Friday, November 7, 2008 11:21:40 AM
Subject: [Vantage] Cost Adjustment


I patched our production Progress database to 406 and now find that the Cost Adjustment program does not work as before. Using the grid to make multiple entries (part number, cost, reason code), it burps after the first entry claiming a bad reason code but lets you click on OK and then proceeds to the next one, and so on. Our CFO doesn't consider this an acceptable solution and the nice people at Epicor say that a fix will be available in 407 due out the end of December. Has this problem been encountered already by anyone else and an alternate solution derived? We don't have Service Connect, so that is out of the question. Any suggestions?
Â
Thanks as always,
-Karl

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]