Costing Burden Rate <> Quoting Burden Rate

--- In vantage@yahoogroups.com, "Brian Stenglein" <bstenglein@...>
wrote:
>
> When, if ever, does it make sense to have these 2 rates be different?
>
> Thanks,
>
> Brian
>

Brian, we don't do it, but conceptually if you what to account for some
inefficiency or pad your qoutes if you are using true engineered cycle
times, you can either change the quoted rates to be a % of actual or
use different rates all togehter knowing certail resources are
inefficient up front.
When, if ever, does it make sense to have these 2 rates be different?

Thanks,