Crystal Report - Lost time for scrap

I am trying to create a report for management that shows us the time lost on scrap pieces. The formula for the lost time on the current operation is ScrapQty/ProdStd. What I need to figure out is the same type of formula but for the lost time on the current scrap pieces / previous operation sequences Prod std.
We had 10 pieces scrap on Op 30. Op 30 Prod Std = 40pph. Lost time is .25 hours.
Now I want the lost time for these same 10 pieces in relation to the previous 2 operations.
Op 10 Prod std = 50 Lost time for these 10 pieces on Op 30 = .20 hours
Op20 Prod std = 20 Lost time for these 10 pieces on Op 30 = .50 hours

Total lost time for these 10 pieces of scrap = .95 hours.

Any one have any idea on how to have the current operation scrap pieces divide into the Prod std for previous operations?

Thanks for your help.



Melissa Hietala
UMC, Inc.