> Post Processing on Quote.Update
>
> FOR EACH ttQuoteDtl:
> Assign ttQuoteDtl.Number10 = ttQuoteDtl. ExpectedSellQty *
> ttQuoteDtl.YourCustomInstllaTimeField.
> END.
>
> *Jose C Gomez*
> *Software Engineer*
> *
> *
> *
> *T: 904.469.1524 mobile
> E: jose@...
> http://www.josecgomez.com
> <http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
> <http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
> <http://www.josecgomez.com/professional-resume/>
> <http://www.josecgomez.com/feed/>
> <http://www.usdoingstuff.com>
>
> *Quis custodiet ipsos custodes?*
>
>
>
> On Wed, Aug 15, 2012 at 8:42 AM, nustepvantage <dpfiester@...> wrote:
>
> > **
> >
> >
> > Hi Chris,
> >
> > Perhaps writing a BPM that would place your calculation in a UD filed in
> > the QuoteDtl table for each part line. I have a post process BPM using the
> > Quote.ChangePartNum method that changes the Product Group field after an
> > ExepectedSellQty has been entered. I would think this would bring in your
> > UD value from the related Part table and then run your calculation fomula.
> >
> > Thanks,
> > David Pfiester
> > Systems Accountant
> > NuStep, Inc.
> > 734-418-1850
> >
> >
> > --- In vantage@yahoogroups.com, "redrhyno13" <cwineinger@> wrote:
> > >
> > > We've added a UD column in parts for Install time and asked to duplicate
> > it on the quote. (done)
> > > Now they want each line to show a calculated field for the Total Install
> > time, a calculated field of the Install time field Times the
> > ExpectedSellQty field on the quote.
> > > Anyone have a good way to accomplish this? I'm out of ideas...
> > >
> > > Thanks,
> > >
> > > Chris Wineinger
> > > ERP Specialist
> > > Interior Systems, Inc.
> > > 241 N Broadway Ste 600
> > > Milwaukee, WI 53202
> > > Office # 414.224.0957 X2051
> > > Direct# 414.847.0701
> > > Cell # 414.840.6594
> > >
> >
> >
> >
>
>
> [Non-text portions of this message have been removed]
>
We've added a UD column in parts for Install time and asked to duplicate it on the quote. (done)
Now they want each line to show a calculated field for the Total Install time, a calculated field of the Install time field Times the ExpectedSellQty field on the quote.
Anyone have a good way to accomplish this? I'm out of ideas...

Thanks,

Chris Wineinger
ERP Specialist
Interior Systems, Inc.
241 N Broadway Ste 600
Milwaukee, WI 53202
Office # 414.224.0957 X2051
Direct# 414.847.0701
Cell # 414.840.6594
Hi Chris,

Perhaps writing a BPM that would place your calculation in a UD filed in the QuoteDtl table for each part line. I have a post process BPM using the Quote.ChangePartNum method that changes the Product Group field after an ExepectedSellQty has been entered. I would think this would bring in your UD value from the related Part table and then run your calculation fomula.

Thanks,
David Pfiester
Systems Accountant
NuStep, Inc.
734-418-1850

--- In vantage@yahoogroups.com, "redrhyno13" <cwineinger@...> wrote:
>
> We've added a UD column in parts for Install time and asked to duplicate it on the quote. (done)
> Now they want each line to show a calculated field for the Total Install time, a calculated field of the Install time field Times the ExpectedSellQty field on the quote.
> Anyone have a good way to accomplish this? I'm out of ideas...
>
> Thanks,
>
> Chris Wineinger
> ERP Specialist
> Interior Systems, Inc.
> 241 N Broadway Ste 600
> Milwaukee, WI 53202
> Office # 414.224.0957 X2051
> Direct# 414.847.0701
> Cell # 414.840.6594
>
Post Processing on Quote.Update

FOR EACH ttQuoteDtl:
Assign ttQuoteDtl.Number10 = ttQuoteDtl. ExpectedSellQty *
ttQuoteDtl.YourCustomInstllaTimeField.
END.

*Jose C Gomez*
*Software Engineer*
*
*
*
*T: 904.469.1524 mobile
E: jose@...
http://www.josecgomez.com
<http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
<http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
<http://www.josecgomez.com/professional-resume/>
<http://www.josecgomez.com/feed/>
<http://www.usdoingstuff.com>

*Quis custodiet ipsos custodes?*



On Wed, Aug 15, 2012 at 8:42 AM, nustepvantage <dpfiester@...> wrote:

> **
>
>
> Hi Chris,
>
> Perhaps writing a BPM that would place your calculation in a UD filed in
> the QuoteDtl table for each part line. I have a post process BPM using the
> Quote.ChangePartNum method that changes the Product Group field after an
> ExepectedSellQty has been entered. I would think this would bring in your
> UD value from the related Part table and then run your calculation fomula.
>
> Thanks,
> David Pfiester
> Systems Accountant
> NuStep, Inc.
> 734-418-1850
>
>
> --- In vantage@yahoogroups.com, "redrhyno13" <cwineinger@...> wrote:
> >
> > We've added a UD column in parts for Install time and asked to duplicate
> it on the quote. (done)
> > Now they want each line to show a calculated field for the Total Install
> time, a calculated field of the Install time field Times the
> ExpectedSellQty field on the quote.
> > Anyone have a good way to accomplish this? I'm out of ideas...
> >
> > Thanks,
> >
> > Chris Wineinger
> > ERP Specialist
> > Interior Systems, Inc.
> > 241 N Broadway Ste 600
> > Milwaukee, WI 53202
> > Office # 414.224.0957 X2051
> > Direct# 414.847.0701
> > Cell # 414.840.6594
> >
>
>
>


[Non-text portions of this message have been removed]