E9 MRP settings

Can you tell MRP not to make suggestions within a certain number of days so there are less suggestions?

Can you run MRP on a single part?

Try setting the “Planning Time Fence” setting, which is found on Part Maintenance - Sites - Planning tab.

Thanks that worked. Can you run MRP on a single part?

Net Change MRP allows single part planning.

I seem to remember that single part MRP was only introduced in E10.

Might even have been 10.1 or 10.2, not even 10.0.700.

thanks

It existed in 8, all you have to do is enter your part number on the part tab, and the system will switch the task to be “net change”. Regenerative does not allow selecting individual items. It’s the whole shootin’ match.

Thanks