E9 queue hours

We have a resource with 40 queue hours. I expect that an Operation in this Resource Group would have a start date 5 days before its due date. This is not happening. I checked the calendar and it’s ok. The resource has the “use Resource Group Values” checked.

Is there something else that would cause this?

@randallweber If you look in the job scheduling board you will see Move and Queue times are different colors and an offset outside of the operation’s Start Date and Due Date.
The progression is QueStartDate - QueStartHour to StartDate - StartHour then DueDate - DueHour to MoveDueDate - MoveDueHour

Thanks - I’ll take a look on Monday. Looks complicated.