Editing production order after partial quantity is completed?

How do you edit a production order after a partial quantity has been completed?

Example: You have completed 4/10 but you need to sub out a component due to lead time on the remaining quantity.

I haven’t run into this yet, but you might be able to edit it from the production order queue.
Orders > Production Order > Transaction > Production Order Queue

If this works, please update the post to let me know

You can use Split Job to move the remaining 6 components to new job. this can be found under the Actions menu.

Would this be in the Production Order Entry screen?

Thank you for the response, David. I tried in Production Order Queue and was not able to do it there.