Epi Binding - Assistance Needed

I’m trying to build a capacity BAQ. I found the ProdCal table that gives the default hours per day section. This data won’t work because we have 5 8 hour days for our first shift and 4 10 hour shifts for our second shift. I then found the production calendar maintenance and it list hours by day the way it should be. The only issue is that they are EpiBindings: HoursPerDay.Hours0-6. How do I track these epibindings to where they are stored?

Or if someone has built a capacity BAQ before what did you use to get the current hours scheduled for each resource group? I would like to avoid manually entering data if possible.