I am (starting to be less) sure that the Receive Time value allows me to walk back the final operation due date of a job x # of days from the job due date.
Are there any other variables that do this as well? I am seeing jobs with a receive time of 3 days but the job due date and the final op due date are 3 weeks apart.
Look at move hours on the resource/resource group. I believe that will have that effect… but you’d see it on all operations that ran through that resource, not just the final operation.
Is it possible anything changed since the last time the job was scheduled? For instance, if you change receive time but don’t reschedule the job, it would still show the improper receive time. Is this an MRP job or manually created job?