Wondering how people handle the requirement for operators to do first and last part inspections and if you are using anything in vantage to regulate it?

Our thought was to have a checkbox on each operation for First Part and Last Part. If first part is not checked then the operator cannot claim parts. If last part is not checked then no other ops can claim parts. If anything this helps make people accountable whether they do the inspection or not. Even if they check the box just so they can claim the part, if we find out later we had a quality issue it can come back to the operator and say, "Well you told the system you inspected it."

Open for any suggestions or BAQ,BAM,BPM's

Vantage 8.03.409C

Toby Boogerd | Information Systems