Force inspection on operation

No - but you can force the NEXT Op to require some minimal qty of 1st piece inspection. Of course that won't help much if it the LAST Op 9as there is no 'next OP).

We actually have OPs for inspection (essentially zero direct cost and resource is infinite capacity)...

This is a legacy paradigm from 2 systems ago and has served us well for 15+ years. It also proved to work on Vantage when we relealized Vantage decided design the product NOT to support Job receipt inspections (as they do for PO receipts). (Talk about reinventing the wheel in software... Why have two paradigms?)

Rob




--- On Fri, 5/1/09, Tony Hughes <thughes281@...> wrote:

From: Tony Hughes <thughes281@...>
Subject: [Vantage] Force inspection on operation
To: vantage@yahoogroups.com
Date: Friday, May 1, 2009, 9:15 AM









Is there a way to force material to inspection at end of a job operation?
Similar to way you do on purchased material.

Thanks.
Is there a way to force material to inspection at end of a job operation?
Similar to way you do on purchased material.

Thanks.