FW: Issue 376492: Problem in Labor entry, unable to delete or e

Does it lock things if you just run the Inventory/WIP Reconciliation or only
when doing the Capture COS/WIP activity?

> -----Original Message-----
> From: Ellapan [mailto:ellapan@...]
> Sent: Tuesday, September 26, 2000 9:57 PM
> To: vantage@egroups.com
> Subject: [Vantage] FW: Issue 376492: Problem in Labor entry, unable to
> delete or edi t labor details for a period of 2 weeks
>
>
> Workaround for this is to use Labor adjustment option under Job
> adjustment but you can't delete the labor entries.
>
> Best Regards,
> Ellappan.
> Megatech Electronics Pte Ltd.
> Singapore.
>
>
> -----Original Message-----
> From: Ellapan
> Sent: Wednesday, September 27, 2000 10:14 AM
> To: vantage@egroups.com
> Subject: FW: Issue 376492: Problem in Labor entry, unable to delete or
> edit labor details for a period of 2 weeks
>
>
> Hi All,
>
> FYI.
> For Vantage 4.00, Pls. don't run "Capture COS/WIP Activity" program till
> your month end closing if you are require to edit labor details anytime
> before month end posting / closing.
>
> When you run the Capture COS/WIP without marking it for posting to GL,
> it still locks down the labor details for editing.
>
> I received the reply from support is:-
> It assumes that a customer who is not interfaced to GL is making manual
> journal entries from
> the reports and in order for the reports to tie out to that entry it
> will still lock down labor entries so they cannot be edited.
>
> Pls. let me know if you need any clarification on the same.
>
> Best Regards,
> Ellappan.
> Megatech Electronics Pte Ltd.
> Singapore.
>
>
Hi All,

FYI.
For Vantage 4.00, Pls. don't run "Capture COS/WIP Activity" program till
your month end closing if you are require to edit labor details anytime
before month end posting / closing.

When you run the Capture COS/WIP without marking it for posting to GL,
it still locks down the labor details for editing.

I received the reply from support is:-
It assumes that a customer who is not interfaced to GL is making manual
journal entries from
the reports and in order for the reports to tie out to that entry it
will still lock down labor entries so they cannot be edited.

Pls. let me know if you need any clarification on the same.

Best Regards,
Ellappan.
Megatech Electronics Pte Ltd.
Singapore.
Workaround for this is to use Labor adjustment option under Job
adjustment but you can't delete the labor entries.

Best Regards,
Ellappan.
Megatech Electronics Pte Ltd.
Singapore.


-----Original Message-----
From: Ellapan
Sent: Wednesday, September 27, 2000 10:14 AM
To: vantage@egroups.com
Subject: FW: Issue 376492: Problem in Labor entry, unable to delete or
edit labor details for a period of 2 weeks


Hi All,

FYI.
For Vantage 4.00, Pls. don't run "Capture COS/WIP Activity" program till
your month end closing if you are require to edit labor details anytime
before month end posting / closing.

When you run the Capture COS/WIP without marking it for posting to GL,
it still locks down the labor details for editing.

I received the reply from support is:-
It assumes that a customer who is not interfaced to GL is making manual
journal entries from
the reports and in order for the reports to tie out to that entry it
will still lock down labor entries so they cannot be edited.

Pls. let me know if you need any clarification on the same.

Best Regards,
Ellappan.
Megatech Electronics Pte Ltd.