Generating an order through purchase order suggestions. Choosing to buy a
different quantity than the computer says to, entering the new qty into the
block and the computer brings that price break forward. Now when you say
yes to generate and then go into the po in the po entry screen the computer
has changed the unit cost to the highest quantity price break. Comments?