Global Forward Scheduling 2 Operations Sequentially

Hi,



Is it possible to use Global Scheduling with Forward Finite to schedule 2
separate operations one after the other?



The example is a part goes through 2 resources where the operations
physically happen straight after each other. The capacity for both resources
is the same, however the first operation only takes 20 minutes whereas the
second takes 50 minutes. This means capacity for the first resource is
available a lot sooner than for the second resource, so is scheduled a lot
earlier.



We are on 9.05.700B and don't have APS.



Thanks,



Darryn