We have not found a way. Be careful when you do issue a different part
number to a specific bom material. The part number in the BOM does not
change, the qty will increase buy the issue qty and the cost will also
increase. This may be OK for parts being substituted intentionally but
is a problem if its a data entry error.
Mark D
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of nmtaylor1969
Sent: Friday, October 24, 2008 9:22 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: How Do I Issue Parts To A Job Which Are Not On
The Original Method ??
Hmmm, I didn't realise you could do that. 8.03.305 appears to have
the same functionality too...
Is there any way I can get it to create a new item on the BOM without
going through the engineering process...??
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Michael McWilliams"
<mmcwilliams22@...> wrote:
number to a specific bom material. The part number in the BOM does not
change, the qty will increase buy the issue qty and the cost will also
increase. This may be OK for parts being substituted intentionally but
is a problem if its a data entry error.
Mark D
________________________________
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of nmtaylor1969
Sent: Friday, October 24, 2008 9:22 AM
To: vantage@yahoogroups.com
Subject: [Vantage] Re: How Do I Issue Parts To A Job Which Are Not On
The Original Method ??
Hmmm, I didn't realise you could do that. 8.03.305 appears to have
the same functionality too...
Is there any way I can get it to create a new item on the BOM without
going through the engineering process...??
--- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
"Michael McWilliams"
<mmcwilliams22@...> wrote:
>any
> In 403c I can issue any part to a job using issue material. The
> material from the BOM comes up as default, but then I can put in
> part number and quantity and it will accept it."nmtaylor1969" <n.taylor@> wrote:
>
> --- In vantage@yahoogroups.com <mailto:vantage%40yahoogroups.com> ,
> >[Non-text portions of this message have been removed]
> > Can any body help with this one Please...?
> >
> > In some cases I need to issue odd bits and pieces to a job which
> are
> > not on the original engineered method BOM...
> >
> > Do I have to un-engineer the job, modify the BOM, and the re-
> engineer
> > the job before I can perform the issue...?
> >
> > Is there any way I can just issue miscellaneous parts and be done
> with
> > it..?
> >
> > The "Issue Miscellaneous Materials" option does not let me issue
> > anything to a job, so its of no help in this instance...
> >
> > Thanks,
> >
> > Nick
> >
>