**What is the best practice regarding a material that has been bought for a job, and is no longer required? **
- The job has been completed and finished but I can’t close it because Epicor doesn’t let you delete the JobMtl line if it’s linked to a PO, and it doesn’t let you change the PO if it’s linked to a Container, even if it hasn’t been receipted yet.
The job has been completed and the material is not arriving for another month.
Should I wait one month to receive the material, and then adjust the job so it issues the material back to inventory, and THEN close the job, or is there a better way to do it?