## Post #1 by @system
We cannot close work orders in a timely manner because of receiving
invoices from our subcontractors. The problem we are facing is when
we complete work orders at less than production quantity the
difference between the completion quantity and the production
quantity remains in WIP. This quantity remaining in WIP has masked
the need to generate a work order to cover remaining requirements.
Two questions. 1. How do other people handle this. 2. Is there a
field I can use in report builder to see what is in WIP.
Thanks
Chuck
---
## Post #2 by @system
Chuck,
We have the same issue here. We have made our own report builder report for
Wip and when jobs are completed on the floor we make the jobs complete but not
closed these complete jobs show at the bottom of the report with their own
completed job(s) total. When all of the sub's have sent in the invoices then we close
the jobs. I hope this helps.
Jeff
Charles Metcalf wrote:
> We cannot close work orders in a timely manner because of receiving
> invoices from our subcontractors. The problem we are facing is when
> we complete work orders at less than production quantity the
> difference between the completion quantity and the production
> quantity remains in WIP. This quantity remaining in WIP has masked
> the need to generate a work order to cover remaining requirements.
> Two questions. 1. How do other people handle this. 2. Is there a
> field I can use in report builder to see what is in WIP.
> Thanks
> Chuck
---
## Post #3 by @system
Jeff,
Would you share this report with me.
Thanks
Chuck
Chuck,
We have the same issue here. We have made our own report builder report
for
Wip and when jobs are completed on the floor we make the jobs complete but
not
closed these complete jobs show at the bottom of the report with their own
completed job(s) total. When all of the sub's have sent in the invoices
then we close
the jobs. I hope this helps.
Jeff
Charles Metcalf wrote:
> We cannot close work orders in a timely manner because of receiving
> invoices from our subcontractors. The problem we are facing is when
> we complete work orders at less than production quantity the
> difference between the completion quantity and the production
> quantity remains in WIP. This quantity remaining in WIP has masked
> the need to generate a work order to cover remaining requirements.
> Two questions. 1. How do other people handle this. 2. Is there a
> field I can use in report builder to see what is in WIP.
> Thanks
> Chuck
---
## Post #4 by @system
jeff, if you don't mind sharing, i'd sure like to see this report too. thx-
james
-----Original Message-----
From: Charles Metcalf [mailto:
chuck_metcalf@...]
Sent: Thursday, October 26, 2000 8:40 AM
To:
vantage@egroups.com
Subject: RE: [Vantage] Job Completion
Jeff,
Would you share this report with me.
Thanks
Chuck
Chuck,
We have the same issue here. We have made our own report builder report
for
Wip and when jobs are completed on the floor we make the jobs complete but
not
closed
---
## Post #5 by @system
Jeff;
We too may be interested in this report.
Warren.Eddy@...
219 478-2363 ext 217
-----Original Message-----
From: Jeffrey Myers [mailto:
myersjg@...]
Sent: Thursday, October 26, 2000 9:11 AM
To:
vantage@egroups.com
Subject: Re: [Vantage] Job Completion
Chuck,
We have the same issue here. We have made our own report builder report
for
Wip and when jobs are completed on the floor we make the jobs complete but
not
closed these complete jobs show at the bottom of the report with their own
completed job(s) total. When all of the sub's have sent in the invoices
then we close
the jobs. I hope this helps.
Jeff
Charles Metcalf wrote:
> We cannot close work orders in a timely manner because of receiving
> invoices from our subcontractors. The problem we are facing is when
> we complete work orders at less than production quantity the
> difference between the completion quantity and the production
> quantity remains in WIP. This quantity remaining in WIP has masked
> the need to generate a work order to cover remaining requirements.
> Two questions. 1. How do other people handle this. 2. Is there a
> field I can use in report builder to see what is in WIP.
> Thanks
> Chuck
We no longer allow attachments to files. To access/share Report Files,
please go to the following link:
http://www.egroups.com/files/vantage/
(Note: If this link does not work for you the first time you try it, go to
www.egroups.com, login and be sure to save your password, choose My Groups,
choose Vantage, then choose Files. If you save the password, the link above
will work the next time you try it.)
---
## Post #6 by @system
Me too......
Bob Bruton
bob@...
jeff, if you don't mind sharing, i'd sure like to see this report too. thx-
james
-----Original Message-----
From: Charles Metcalf [mailto:
chuck_metcalf@...]
Sent: Thursday, October 26, 2000 8:40 AM
To:
vantage@egroups.com
Subject: RE: [Vantage] Job Completion
Jeff,
Would you share this report with me.
Thanks
Chuck
Chuck,
We have the same issue here. We have made our own report builder report
for
Wip and when jobs are completed on the floor we make the jobs complete but
not
closed
[Non-text portions of this message have been removed]
---
## Post #7 by @system
Does anyone know where the number in the relieved quantity field in
manufacturing links comes from.
Thanks
Chuck
---
## Post #8 by @system
For the bottom left browse it's JobProd.ShippedQty + JobProd.ReceivedQty.
For the top right browse of jobs it's JobHead.
ShippedQty + JobHead.ReceivedQty.
---