Job Demand Link Relieve Order?

Hey There,

Does anyone happen to know the order in which Demand Links, on a job, get relieved when the Final Op is set as Auto Recieve and a QTY is completed? I’m modifying a BPM that creates a bartender label that accompanies the finished parts to the next location.

Let’s say I have the following Demand Links on a job:

  • 10 to stock
  • 20 to another job
  • 5 to a sales order.

If someone completes 15, what decides the order in which those 15 get issued? Is there a Sequence or index field for the records? I’m assuming I can just loop through the JobProd records, and that will be the same order the AutoReceive is using, but wanted to see if anyone knew for sure.

Thanks!