First, some background info. My company is in the stone age as far as their implementation of Epicor - we are still have not upgraded to Kinetic and will not be doing so for at least another year (apparently we made absolutely way too many customized fields / screens when they first adopted it and everything has to be redone from scratch in Kinetic). The other issue is that they have never truly implemented any of the core tools Epicor provides and therefore don’t really have any knowhow on how to actually run things in Epicor. We have no on-site expert and don’t have any sort of training on how to use the software. We’re running on band-aids and hopium, in all honesty.
My production team has issues pushing jobs through the operation steps frequently, because they code the jobs for say 60 pieces and don’t account for scrap at any of the operation steps. So Epicor expects to see 60 good/completed pieces at the end of the final operation in order to close out the job, but we may only have 59 because they scrapped one. Until this point, operations would either just kind of grab another material and make the 60th part without capturing it (so technically they would use 61) or just drop the job quantity from 60 to 59 to allow the operations to be completed. Now that I’m trying to implement actual quality tools/data captures for KPI’s, things are getting difficult. We have the operators not able to complete out their steps (say Op 20) due to not having the correct quantity of parts to complete out, so they just physically move it on and don’t do anything in the MES to push the job, since they can’t complete the step if they have 59 of 60 completed. This is putting a major strain on my final inspection team because they are receiving jobs where 2 to sometimes 5 operations haven’t been completed yet in Epicor but physically the parts are ready for final inspection. I have started getting some operators to begin using the Nonconformance entry when they have a nonconforming part, but not all (I’m still trying to get the training in place and have supervisors push the issue with people).
I found on the Job Entry screen that there is a place for putting in scrap rates at the operation level, but I don’t know how it works and I couldn’t find a previously discussed topic thread for it (could be I just wasn’t hitting the right buzzwords). Is there a way to put in a scrap rate for the whole job? It looks like at the operation level, I can dictate either by quantity or by percentage of the job total; is there a way to apply that to the whole job or do we have to set it at each operation each time we make a job?
If we can input a scrap rate on some of these jobs and it would allow the operations to continue flowing that would be a big help. My initial thought was to basically dictate a straight quantity, so for example if the job is 60pcs put in a scrap of 5pcs, so my thinking is it would bump the production value to 65, and allow the job to flow operation-to-operation as long as we have 60pcs good or more. After seeing that it’s tied to the individual operation (screenshot above), I am not sure if that’s how it can work now. Can someone explain how that highlighted section functions?
My next question is related to what do we need to do when a part is contained as a nonconformance? I would think that if we issued enough raw material to make 60 parts, we would need to issue 1 extra raw material piece to make up for the one that was scrapped (60 total OK, 1 scrap). However, this seems to cause issues because when we tried this this week it pushed a job from a total of 40 completed to a total of 42 completed. My final inspection team had to “pass” -2 parts in order to close out the operation step to get it to balance out. For clarification, it said operation 10 completed 42 parts, but the operator created a nonconformance on op 10 for 2 parts and it didn’t capture it in the job data for some reason. So he ended up passing 42 parts OK parts instead of 40 OK and 2 Nonconformance while still having an active nonconformance record for 2 parts. Final inspection was Op 20 and since the job total quantity due was 40 it required a -2 to be input to end the task/close it out. What is the proper way of handling adding in additional material? Or should we always just reduce the due quantity and create a second job for the missing pieces (so for the above example it would have been 38pc and 2pc jobs)? Obviously something screwed up with the reporting, I’m just not sure what since the record was updated/changed so many times before I could look at it and I guess that isn’t recorded in the change log. I imagine it was a data entry error but the operator doesn’t remember since this apparently happened over a week ago (and they just informed me yesterday). We jerry-rigged a solution for this one, but I would like to know how to do it the correct way for the (inevitable) next time.
Sorry for the long post, hopefully it all makes sense.

