Job Operation Reject from DMR Not Working Properly

Hello,

When Job Operation is being reject from DMR, its not affecting the LaborDtl and JobOper Table. I have not understood the logic.
For Eg ProdQty is 10. I have 2 Operation. Labor REport 10 Pcs in MES for Opr 1 and 2. So both Opr is complete. But later found some issue in Opr2 for 5 pcs. So I will put 5 pcs in NonConf from MES. Then in DMR i will reject . But this 5 Reject is not affecting the Opr 2 Complete Qty. In JobOper its still showing 10 pcs as complete but phycially I have reject 5 pcs in DMR.
When checking the DMRActn table, in that JobNum and Oprseq is blank.

How or what setting is there so that once any JobOperation , DMR is reject it should affect in Job Level also.

Thanks.

image

Hi,
Thank you for reply.
This option is already tick. Also i belive this is only for Cost.

But for me, Qty is not affecting when from Job Operation is scrapped through DMR and its not affecting the JobOper table .

Are the employees entering that they completed 10 when they only completed 5 and scrapped 5? Rejecting a DMR does not change any quantity on the job as that quantity was already entered at the operation to move it to NCR.