Hello,
Job Operations are showing in red color triangle, and the operation start date and end date were greyed out. How to edit dates?
Hello,
Job Operations are showing in red color triangle, and the operation start date and end date were greyed out. How to edit dates?
Those dates are calculated automatically when you schedule the job. Try to reschedule the job. You can’t edit those dates directly, the scheduling tool does that.
Thank you, Nate. What does the red triangle represent? We are only unable to edit this, while the other operations are not greyed out
An operation that has not been run yet. This icon may also be coupled with the “tag with a red dot” icon to indicate that there are material constraints for the operation.
Use Job Scheduling Board to move operation to the date and time you want. There are some options for you to move: Operation Only; All Job; Preseeding Operation, SubSequent Operation;.. try to test this to know more. Of course you also do it on Resource Scheduling Board or Multi Resource Scheduling Board; or DMT by using Schedule Job
We’ve always manually entered the dates.