I think in your original post you mentioned 8.03.404b...there were several issues with 404b and scheduling.

We upgraded to 405 (no patches) last fall and scheduling (for the most part) has been bug free and reliable.

Thanks
Patty Buechler

--- In vantage@yahoogroups.com, Steven Gotschall <sgotschall@...> wrote:
>
> We had a problem where assemblies dropped out of the schedule and we found out that the method was being changed on the job after it was Engineered and scheduled. Maybe you are running into something like that. Try to unengineer the job and then reschedule it.
>
>
>
>
> ________________________________
> From: Vic Drecchio <vic.drecchio@...>
> To: vantage@yahoogroups.com
> Sent: Thursday, August 13, 2009 10:15:03 AM
> Subject: [Vantage] Job Ops not being Scheduled
>
> Â
> (8.03.404B SQL)
>
> Has anyone ever experienced jobs and operations *not* being scheduled?
>
> I had a post to the group earlier in the week about the Priority
> Dispatch report and certain operations not being on the report.
>
> I pulled up two consecutive almost-identical jobs and evaluated each for
> differences and found none. One job had Opr 25 scheduled as expected
> but the other job won't get scheduled.
>
> When I run MRP I run a Net-Change with "Run Finite Scheduling" unchecked
> and "Allow Historical Dates" unchecked. All other options are enabled.
>
> Of course Support says "upgrade" to .408B.
>
> Thank you in advance.
>
> Vic
>
> Vic Drecchio
> ERP Administrator
>
> TIMCO Aviation Services
> Greensboro, NC
> Email: vic.drecchio@ timco.aero
> Mobile: 704.530.3092
>
> [Non-text portions of this message have been removed]
>
>
>
>
>
>
>
> [Non-text portions of this message have been removed]
>
(8.03.404B SQL)



Has anyone ever experienced jobs and operations *not* being scheduled?



I had a post to the group earlier in the week about the Priority
Dispatch report and certain operations not being on the report.



I pulled up two consecutive almost-identical jobs and evaluated each for
differences and found none. One job had Opr 25 scheduled as expected
but the other job won't get scheduled.



When I run MRP I run a Net-Change with "Run Finite Scheduling" unchecked
and "Allow Historical Dates" unchecked. All other options are enabled.




Of course Support says "upgrade" to .408B.



Thank you in advance.







Vic





Vic Drecchio
ERP Administrator

TIMCO Aviation Services
Greensboro, NC
Email: vic.drecchio@...
Mobile: 704.530.3092



[Non-text portions of this message have been removed]
We had a problem where assemblies dropped out of the schedule and we found out that the method was being changed on the job after it was Engineered and scheduled. Maybe you are running into something like that. Try to unengineer the job and then reschedule it.




________________________________
From: Vic Drecchio <vic.drecchio@...>
To: vantage@yahoogroups.com
Sent: Thursday, August 13, 2009 10:15:03 AM
Subject: [Vantage] Job Ops not being Scheduled

Â
(8.03.404B SQL)

Has anyone ever experienced jobs and operations *not* being scheduled?

I had a post to the group earlier in the week about the Priority
Dispatch report and certain operations not being on the report.

I pulled up two consecutive almost-identical jobs and evaluated each for
differences and found none. One job had Opr 25 scheduled as expected
but the other job won't get scheduled.

When I run MRP I run a Net-Change with "Run Finite Scheduling" unchecked
and "Allow Historical Dates" unchecked. All other options are enabled.

Of course Support says "upgrade" to .408B.

Thank you in advance.

Vic

Vic Drecchio
ERP Administrator

TIMCO Aviation Services
Greensboro, NC
Email: vic.drecchio@ timco.aero
Mobile: 704.530.3092

[Non-text portions of this message have been removed]







[Non-text portions of this message have been removed]