Job or operation changing site

Hello everyone,
We are preparing Epicor and have not yet transitionned to it, it’s scheduled next year. One challenge we are facing is site management. We have two plants with the same activities and operations, but with different financial accounting, so we are going towards one ompany but two sites.

One thing we do frequently is change the site where a job is done (it would be scheduled on site 01 but then moved and done on site 2).
Another thing is we sometimes do some operations of the job on site 01 and some on site 02.
Both of these changes are done on-the-fly, meaning the job could already be started and we would send it to be finished on the second site in the same day.

The way we think it could work would be to implement alternate methods for such parts, and then change the job site and method in the first case.
In the second case, we’re thinking to implement subcontracting operations in each site, and then change operations in the job to subcontract it to the second site.

These seems a little over-engineered in my eyes but I don’t have the experience of Epicor to be a good judge of that. Do you think its doable this way ? or in another way ?

Thanks in advance.

I have a ubaq that flexes a job from one resource group to another and we just got another plant in our group that can build what we build so I am investigating flexing sites on inprocess jobs. It is a bit more complex since jobs, resource groups and resources are site specific, but it should be doable just not out of the box.

Thanks for your input.

Hi Greg,

Were you ever able to get a customization working to allow the same job to be processed in different sites? I’m looking into this too - but in our environment we use backflush labor and material, so it adds even more complexity…

Thanks,

Jenn

We have not gotten the second plant running yet so it has not been needed.

Anyone look into shared warehouses? That might help the backflushing… I’m not sure what complexity that introduces, though.

Interesting concept - shared warehouses. There is a shared warehouse with customer provided components, but those are issued to the job manually.

In this case, both sites stock the same components (with cycle counting) and can do most of the same work. When I change sites in MES - I can log into the site the job was created in and complete an operation - but the materials all backflush from the site the job was created in. I figured it would.

Going to be “fun” figuring out how to customization flexibility to move jobs between sites at any point in the process.

You should not have to customize, you should just use Alternate Revisions Methods.

That works for easily toggling between which site to do the job in… but how does that help if you want to start a job in one site and finish it in another? I didn’t think that would solve that problem.

I did not catch the start and finish. I thought it was more, a job was released in Site A, no work started on it, and we want it now in Site B. I agree, I don’t think Alternate Method would work in that situation

I believe the only way you could do this is by editing the job by removing the operations that are not done, and adding them back in the second site. Then you would need to do a transfer order of the WIP to the other site.

This is what we do.

A function creates a receiving job and removes the operations we need to.

The receiving job has a material that is marked “make direct” and which origin is the sending job’s plant.
When the sending job is complete, we run a job receipt to job from the sending to the receiving job, which creates a Transfer Order and ship it.
Then the receiving job runs a “Receive transfer order” then complete the sending job.
The orignal demand is made anew on the receiving job and the shipping plant is changed.

It is up to you what you want to do. You don’t have to create the new job. You could use the existing job and just change the operations to the other site. Actually, thinking about it now, can you add operations to another site on a job? I only ever made multi-site jobs in engineering workbench. That is, ops 10-30 were at site A, 40 was at site B, and 50-60 were back at site A.

I didn’t know this was doable :shaking_face: , how do you achieve this ?

I understood that plant is enforced at the job head level, how can it be set at the operation level for MES and production purpose ?

So, you need to set up each Operation that can be done in each Site with their own Scheduling Requirements. If I remember correctly (it has been a few years) you need to be in the Site that you want to add the scheduling requirements to.

Let’s imagine a fresh install with 1 Company and 2 Sites. You go into Site A and create the Operation and put the Scheduling Requirements for Site A. You then close out of Operation Maintenance and switch to Site B. Open Operation Maintenance and select the Operation you just created in Site A. Now add the Scheduling Requirements for Site B to that Operation. Now you have both Sites set up for that Operation.

When creating a MOM, just select the Scheduling Requirement that you want for that step in the router. It can be from either Site and which one you choose dictates how the job flows.

If you have both Sites set up for the same Operation now, you could try changing the Scheduling Requirement on the Operation you want to switch Sites. I never tried it, but it should work.

We are already setup with resources on both sites for each operations.
You can indeed change the scheduling requirements at job-level and engineering-level.

But once the job is started, everything seems to be tied to the “plant” field on JobHead. Material issuing and MES use this one, and I don’t seem to be able to change it at will.

This is why we have two jobs right now. I didn,t find a way to start a job in site 01 and then finish it in site 02.

Did you build a single MOM with the scheduling resources from the sites? When I had this working (years ago) it started in one site, went to another, and then came back to the original site and that worked. It created transfer orders at the end of the operation to transfer to the other site. But this was 3+ years ago.

In our current system it does work with multiple jobs and transfer orders.

My question was how to do it in he same job, litterally moving the job to the other site.

That is what I am saying, you need to create a single method for the 2 jobs that you have now. The system will know when the next operation is in the other site and create a transfer order to move the WIP to the other site. You need a single method in the starting site and adding operations tied to the scheduling resource in the second site makes Epicor behave like it is a subcontract. But instead of having to do a subcontract shipment, you do a transfer order instead.