Hi Amy,
Thanks.
What about the leadtime of the purchase parts? Does the shedule
consider the leadtime requirement to buy the material (purchase
components)? If not, is there work around to make it works.
Nam
Thanks.
What about the leadtime of the purchase parts? Does the shedule
consider the leadtime requirement to buy the material (purchase
components)? If not, is there work around to make it works.
Nam
--- In vantage@yahoogroups.com, "progress92000" <nvong@m...> wrote:
> Hi Group,
>
> I am having a problem to add leadtime of sub component parts to a
> parent job.
>
> Parent part #A with manual job and scheduled start date 09/22/05
and
> due date 09/29/05
>
> The materials use for part #A are manufacturing parts #B and #C
>
> When I ran MRP, the two jobs created with the start date 09/21/05
and
> due date 09/27/05. ??? the materials not ready to build the parent
part.
>
> How can I make the system considers the lead time of the part #B
and
> C# ?
>
> Any suggestions for solutions?
>
> Thanks,
>
> Nam