Sorry this got posted with no subject.
--- In vantage@yahoogroups.com, "A Mercer Sisson" <onelist@i...>
wrote:
--- In vantage@yahoogroups.com, "A Mercer Sisson" <onelist@i...>
wrote:
> I have just observed a job which has operations with no WorkCenteropen a
> (Vantage 6.1.129) . This observation occurred when we went to re-
> job and were told that it has workcenters in different plants (orplant). In
> something like that, which is curious since I have only one
> fact, I was a little surprise to see that about 2/3 of the ops hadno
> workcenter at all!had
>
> Since this worried me I wrote a simple BAQ to see what other JobOps
> no workcenter and sure enough I found 137 JobOps form 17 jobswithout
> workcenters, on further investigation I discovered that every jobwas
> the "target" of the JobSplit function and that all clearedworkcenters
> must have been completed ops at the time of the split and so no onehad
> trouble recording time subsequently. Many (but not all) of theseJobs
> have been around from previous versions of Vantage.occurring.
>
> I have not determined exactly what conditions cause this problem to
> occur on JobSplit since other Jobs have been split without it
> I thought perhaps others might have seen and investigated thisproblem
> as well. I have reported it to tech support - but since they couldnot
> recreate the problem on the first try - they are not sure whataction to
> take.
>
> Has anyone else seen this situation? You might want to check your
> database for it.
>
> Mercer Sisson
>
>
>
> [Non-text portions of this message have been removed]