Kanban Blank Title 106784

We are currently running Vantage 6.1 and experimenting with the Kanban feature. Everything is working as expected except for the GL transactions. The labor & overhead costs are hitting the general COGS variance account. I would have thought the labor & overhead would hit their respective Applied accounts? I thought maybe I have something set up wrong but can't find any GL set up for Kanbans. Does anyone know if this is a bug or am I missing something?

Kathy Hambleton
Electron Energy Corporation


[Non-text portions of this message have been removed]
Is there a way for Vantage to absorb overhead when using machine hours in an automated production process. Ideally there would only be a MES labor punch when a part is moved out of the operation. It appears that Vantage will only absorb the overhead cost up to the number of hours actually applied in the labor punch.