jpol
(Judy Poling)
1
We recently started making our Jobs “Make to Order”.
It’s been observed that when this is done Job Manager show’s the demand as two lines. let me show you an example:
This is Job Manager:

This is the Sales Order Line:
Does anyone know why Job Manager is splitting the demand?
Thank you!
bordway
(Bruce Ordway)
2
I wonder if there are any settings in your part master
sheet sites → planning → lot sizing fields (or sites → detail)

Or if you have run MRP with an elevated logging level - if those contain any clues?

jpol
(Judy Poling)
3
We have a Min Lot Size of 6,000 but that’s it.
I haven’t checked into the elevated logging level but how would that effect this - does it have to do with how the elevated logging level is set-up?