Mass Re-Schedule of Jobs

Hi Darryn;

There is a way; you can use Global Scheduling for this purpose.

Its a three step process

01. Use the option Calculate Global Scheduling Order

02. Adjust Global Scheduling Order

03. Global Scheduling.

I am not sure whether you have the license for using these options. These options are available in Vantage 8.03.408B

Regards

Sreejith J


________________________________
From: Darryn Ralph <darrynralph@...>
To: vantage@yahoogroups.com
Sent: Wednesday, November 21, 2012 4:27 PM
Subject: [Vantage] Mass Re-Schedule of Jobs


Â
Hi,

Is there a way to have a selected list of jobs, change the due dates and
then re-schedule all? We don't have any of the advanced modules and
currently the only way we can do this is one job at a time.

Thanks,

Darryn

[Non-text portions of this message have been removed]




[Non-text portions of this message have been removed]
Hi,



Is there a way to have a selected list of jobs, change the due dates and
then re-schedule all? We don't have any of the advanced modules and
currently the only way we can do this is one job at a time.





Thanks,



Darryn







[Non-text portions of this message have been removed]