Hi Darryn;
There is a way; you can use Global Scheduling for this purpose.
Its a three step process
01. Use the option Calculate Global Scheduling Order
02. Adjust Global Scheduling Order
03. Global Scheduling.
I am not sure whether you have the license for using these options. These options are available in Vantage 8.03.408B
Regards
Sreejith J
________________________________
From: Darryn Ralph <darrynralph@...>
To: vantage@yahoogroups.com
Sent: Wednesday, November 21, 2012 4:27 PM
Subject: [Vantage] Mass Re-Schedule of Jobs
Â
Hi,
Is there a way to have a selected list of jobs, change the due dates and
then re-schedule all? We don't have any of the advanced modules and
currently the only way we can do this is one job at a time.
Thanks,
Darryn
[Non-text portions of this message have been removed]
[Non-text portions of this message have been removed]
There is a way; you can use Global Scheduling for this purpose.
Its a three step process
01. Use the option Calculate Global Scheduling Order
02. Adjust Global Scheduling Order
03. Global Scheduling.
I am not sure whether you have the license for using these options. These options are available in Vantage 8.03.408B
Regards
Sreejith J
________________________________
From: Darryn Ralph <darrynralph@...>
To: vantage@yahoogroups.com
Sent: Wednesday, November 21, 2012 4:27 PM
Subject: [Vantage] Mass Re-Schedule of Jobs
Â
Hi,
Is there a way to have a selected list of jobs, change the due dates and
then re-schedule all? We don't have any of the advanced modules and
currently the only way we can do this is one job at a time.
Thanks,
Darryn