Methods - 10.2.300

Hi All,

I have to setup a method for the part where one of operations in the middle of the process is done on another site.
What is the best practice for that?

We are setup with two sites and both are manufacturing.

big thank you for any suggestions.

Many Thanks
Jarek

I am sure there are different ways to approach this. My approach will be creating 3 part.

Part A => Part B => Part C

Site 1 makes Part A and Part C.

While Part B requires Part A as material.
and Part C requires Part B.

There are processes require for transfering material from one site to another.

1 Like

Hi,

Thank you for your reply. We don’t really want to create middle part number, but i think this the only way :frowning: