We currently do not own project module and are using 10.2.300. My AR group has approached me to see if we can setup some kind of Milestone billing. The main issue is that they have way too many terms codes setup to more or less do the invoicing as “projects” are moving along; 50% at drawings approval, 25% for the first 10 complete, etc. So we have a terms that will be 502525. How can we do this? In reality the terms are typically 30 - 60 days but the invoicing is based on milestones. Is there a way or are we forced to get the project module. We will be upgrading with the next 6 months to a year to latest Kinetic version, so this may be moot if we decide to get project module prior to that.
1 Like