Thank you. No, we do not have
criteria set. I’m not sure if dates
would work, I will check with my Finance Manager, but we aren’t going to know
dates ahead of time in most cases. Can you explain in
a bit more detail how you use phases for this?
—In vantage@yahoogroups.com, <blarson@…> wrote:Did you place a criteria on the Milestone
If there is none, it will complete.
If you want to do it manually, use the date feature - with a date out into the future.
We have been using Phase as our means to complete the milestones…
—In vantage@yahoogroups.com, <scooley@…> wrote:We will put a milestone on the project to be used at a later date, and overnight it appears to auto-complete (the complete checkbox is checked the next day). We have no processes scheduled other than E9 defaults.
We are running E 901 701