Just do a right click on the top assembly, delete all, then right click
again, and get details.



M. Manasa Reddy
manasa@...
P: 630-806-2000
F: 630-806-2001


________________________________

From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Gary Wojtowicz
Sent: Thursday, September 24, 2009 8:32 AM
To: vantage@yahoogroups.com
Subject: [Vantage] MOM Refresh




I had to make changes to the method of manufacturing after the job has
been entered.
How can the job be refreshed with the new MOM or do I have to delete
existing MOM and pull in ne one?

Gary Wojtowicz
AJR Industries, Inc.

[Non-text portions of this message have been removed]






[Non-text portions of this message have been removed]
I had to make changes to the method of manufacturing after the job has been entered.
How can the job be refreshed with the new MOM or do I have to delete existing MOM and pull in ne one?

Gary Wojtowicz
AJR Industries, Inc.



[Non-text portions of this message have been removed]
If the MOM has been changed in the engineering workbench and revision approved and checked back in then you can go and get the details and pull those into the job

--- On Thu, 9/24/09, Gary Wojtowicz <ajrgary@...> wrote:


From: Gary Wojtowicz <ajrgary@...>
Subject: [Vantage] MOM Refresh
To: vantage@yahoogroups.com
Date: Thursday, September 24, 2009, 9:31 AM


Â



I had to make changes to the method of manufacturing after the job has been entered.
How can the job be refreshed with the new MOM or do I have to delete existing MOM and pull in ne one?

Gary Wojtowicz
AJR Industries, Inc.

[Non-text portions of this message have been removed]



















[Non-text portions of this message have been removed]
A Job MOM cannot be 'refreshed'. If no activity has been recorded, you
can delete the details and get the new details. Otherwise, manually
update the job(s) with the correct materials and/or operations.



Charlie Smith

Smith Business Services / 2W Technologies LLC

www.vistaconsultant.com <http://www.vistaconsultant.com/> /
www.2WTech.com









From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf
Of Gary Wojtowicz
Sent: Thursday, September 24, 2009 9:32 AM
To: vantage@yahoogroups.com
Subject: [Vantage] MOM Refresh





I had to make changes to the method of manufacturing after the job has
been entered.
How can the job be refreshed with the new MOM or do I have to delete
existing MOM and pull in ne one?

Gary Wojtowicz
AJR Industries, Inc.

[Non-text portions of this message have been removed]





[Non-text portions of this message have been removed]