MRP Cut Off Date for a specific part exist?

Good day Epicor Kinetic experts,
We have been using MRP for 3 years now and continuously learning about other features that may be beneficial to us . We know that when running MRP, you can set up a MRP cut off date which applies to all parts. Does anyone know if there anything that is part specific MRP cutoff date?
Appreciate any response on this inquiry.

1 Like

I don’t think there is a setting like that at the part level.

You can, however, run MRP on a filtered list of parts. You could possibly achieve what you want by having different MRP runs with different parameters, filtered down to the specific parts or part classes, etc. you want different cut off dates for.

Does the MRP Technical reference provide any insights. @jkane?

No, nothing I can think of. What @hackaphreaka said would be the easiest way to accomplish this.

I was going to say that they could maybe edit the MRP engine, but I do not see those screens anymore. Wonder when they were removed.