We added some sub-assemblies (manually) to a job after an engineering BOM change. MRP did not create suggestions. We deleted the job, and loaded a new job from the BOM and MRP worked.
Thanks inn advance.
Randall Weber
We added some sub-assemblies (manually) to a job after an engineering BOM change. MRP did not create suggestions. We deleted the job, and loaded a new job from the BOM and MRP worked.
Thanks inn advance.
Randall Weber
Hi Randy,
Did you reschedule the job after adding materials? If we forget to reschedule we do not get demands as expected.
Nancy
Yes. But new info: Someone else deleted all materials, then get details and that seemed to work. Need to retest, but it seems odd that the second pass worked.