On Job Entry you can check "lock" on the scheduling options and MRP will ignore this job and leave it along. Any new demand will suggest new jobs instead of changing/rescheduling the current locked job
Â
On the PO release, you can lock the date and/or quantity to do the same thing

--- On Thu, 9/17/09, m_sprowles <msprowles@...> wrote:


From: m_sprowles <msprowles@...>
Subject: [Vantage] MRP Problem/Question
To: vantage@yahoogroups.com
Date: Thursday, September 17, 2009, 1:23 PM


Â



How can we lock a purchase order and/or Job date and quantity in a stock environment where MRP will recognize locked jobs and purchases as filling a demand without suggesting the job/po date be moved or changed without using the make direct option?

Example:

Sales Order 1 is entered for part number A for a qty of 2 to ship 11/1/09

Job 100 is entered for part number A for a qty of 2 to be completed by 11/1/09 – I would like to lock this schedule in place so that if Sales Order 2 is entered for part number A for a qty of 1 to ship by 10/15/09, I would like to get a un-firm job for Part number A for a qty of 1 to be complete by 10/15/09 instead of a suggestion to expedite job 100 to 10/15/09 and reduce the qty from 2 to 1 and then create an un-firm job for a qty of 2 to be completed by 11/1/09 as it does today.



















[Non-text portions of this message have been removed]
How can we lock a purchase order and/or Job date and quantity in a stock environment where MRP will recognize locked jobs and purchases as filling a demand without suggesting the job/po date be moved or changed without using the make direct option?

Example:

Sales Order 1 is entered for part number A for a qty of 2 to ship 11/1/09

Job 100 is entered for part number A for a qty of 2 to be completed by 11/1/09 – I would like to lock this schedule in place so that if Sales Order 2 is entered for part number A for a qty of 1 to ship by 10/15/09, I would like to get a un-firm job for Part number A for a qty of 1 to be complete by 10/15/09 instead of a suggestion to expedite job 100 to 10/15/09 and reduce the qty from 2 to 1 and then create an un-firm job for a qty of 2 to be completed by 11/1/09 as it does today.