Is there a way to have MRP give suggestions for adjusting mins/max levels by part based on a trailing 3 month average?
Hi Grant,
Not sure if you have used the function in Epicor Min Max Safety Mass update - this can be used to update the Min Max as well
There is a tool in epicor Update Min Max Safety Stock.
It looks at average usage per day and suggests updates to min/max/ss based on usage within lead times.
You need history to make it work.
Setup a few parameters in your part classes to make it work.
The dashbaord will allow you to make changes to the suggestions and save from there.
Awesome tool.
Thank you. Any idea how many months of history or number of transactions are required before it starts giving suggestions?
It will use what you have, I would guess you want at least a few months of good transactional data. you can control how far back it looks. The setting are on the part class, I believe you can override on the part as well.