MRP Update Mins/Max Levels Based on Averages?

Is there a way to have MRP give suggestions for adjusting mins/max levels by part based on a trailing 3 month average?

Hi Grant,
Not sure if you have used the function in Epicor Min Max Safety Mass update - this can be used to update the Min Max as well

There is a tool in epicor Update Min Max Safety Stock.
It looks at average usage per day and suggests updates to min/max/ss based on usage within lead times.
You need history to make it work.
Setup a few parameters in your part classes to make it work.
The dashbaord will allow you to make changes to the suggestions and save from there.
Awesome tool.

1 Like

Thank you. Any idea how many months of history or number of transactions are required before it starts giving suggestions?

It will use what you have, I would guess you want at least a few months of good transactional data. you can control how far back it looks. The setting are on the part class, I believe you can override on the part as well.

1 Like