My company thinks they can switch ERP systems in just 14 months

You’ll should get a kick out of this. My current company (not the one I worked at when I was an Epicor user/admin) just signed the contracts with our soon to be new ERP supplier.

Next Monday is the kickoff meeting for the transition, with goals of having the sandbox up and running by March 2027, and going live in Jan 2028.

The current system is a hodge podge of homebrew, IBM LX, Salesforce, external 3rd party MRP proccesor, 3rd party configurator, and probably more that I’ve not been exposed to.

And this transition is going to include rolling in our ER (Engineering Request, i.e ECN) system, document control system, among others.

And we a multinational company with a dozen manufacturing facilities - mostly from acquisition of small companies (like mine), that are only partially integrated with the current systems.

When I heard the Jan 2028 date, my first thought was to go to Kalshi and bet heavily on the OVER.

On the plus side I have little involvement. I was originally on the team, but was then “excused for being too negative” by bringing up many potential issues. Apparently they value cheerleaders over problem identifiers/solvers.

I usually lead with 6-9 months, 12 if it’s more complex. Hard for anyone to really comment without having the inside track on lift involved.

You usually know what you’re talking about, so it’s sounds fun! We’re here to support you, most of what we do here therapy :rofl:

Congrats! “Too negative” and “setting boundaries” can sometimes be two sides of the same thing.

Dedicated team and drive, it can be done.
Depends on the people.

That would be funny if it was listed on there.

If all that was shared was the timeframe, I wouldn’t give it a hands down improbable, as that’s actually a generous timeframe for a smaller company that doesn’t have very complex or broad production flows.

However, 12 different facilities and multi-national ~ I have to agree that’s pretty ambitious and likely overly optimistic (even without knowing what ERP software was chosen). To be honest, consider it a blessing that you were left off of the team. If things go south on that rushed timeline, the implementation team will probably end up shouldering the blame.

Culture, culture, culture and good leadership can get that done.

One of the important things is also having people on the team that can play devils advocate. That is not being negative, but pointing out the potential pitfalls early.

Everyone in the team should be making sure they have done lots of prereading, about ERP implementations.,and understand how the incombant ERP works and how they see it fitting in with their part of the business. These initial steps are crucial to the project success.

Finally ensuring there is adequate backfill for team members to work on the project with the excuses of “Oh but I have my day job to do as well as this project”

Not untrue.

But keep in mind that neither the NY Jets nor the Miami Dolphins have yet been mathematically eliminated from the Super Bowl.

E-A-G-L-E-S EAGLES!

Wasn’t there some company that implemented in 1 week…

Sounds familiar…

THIS! Plus the team needs to have people who pay attention to details and aware of edge cases.

Something to also account for is determining which products they already use which make sense to still use but with integrations into Epicor. If they use SalesForce for their CRM then it can make sense to keep using that and to use API to create the Sales Orders within Epicor, but those decisions do take alot of planning and troubleshooting. Sounds like fun all around.

As long as the phrase, “That’s the way we’ve always done it” has been stricken, software implementation can be fairly quick. Extracting the processes from the current “system” and then finding a best way to implement that into the new system (if even required) is where we spend a lot of time.