Dude, Kanban is such an antiquated manufacturing practice. JIT and LEAN are
the same thing and can be easily managed within the normal production module
without Kanban.

I'm just curious, why does anyone still use Kanban techniques?

Kanban just reminds me of a paper-tape-punch and reader.

-----Original Message-----
From: vantage@yahoogroups.com [mailto:vantage@yahoogroups.com] On Behalf Of
Jose Gomez
Sent: Friday, April 12, 2013 3:03 PM
To: Vantage
Subject: Re: [Vantage] Re: Oh Kan Ban < 1

So Is spoke to Epicor Serveral times, did a web ex and now they came back
and said. We are able to replicated in all versions all the way through 9.
WTF has no one ever reported this? hahah. So they are gonna fix it, for you
9 people. We lowly 8 people are scrwed! But Cest La Vie!


*Jose C Gomez*
*Software Engineer*
*
*
*
*T: 904.469.1524 mobile
E: jose@...
http://www.josecgomez.com
<http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
<http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
<http://www.josecgomez.com/professional-resume/>
<http://www.josecgomez.com/feed/>
<http://www.usdoingstuff.com>

*Quis custodiet ipsos custodes?*


On Thu, Apr 11, 2013 at 6:53 PM, richard_bacon@... <rbacon@...
> wrote:

> **
>
>
> Not that I know of, since that's supposed to be one of the benefits of
> Kanban Receipts (Auto job creation, labor/mtl issuing, and job closing).
>
> --- In vantage@yahoogroups.com, Jose Gomez <jose@...> wrote:
> >
> > Any way to not have the Kaman auto close?
> > On Apr 11, 2013 5:56 PM, "richard_bacon@..." <rbacon@...>
> > wrote:
> >
> > > **
>
> > >
> > >
> > > Yes, we would regularly complete Kanban Receipts of 0.5 or 0.75. I
> would
> > > have to open the job, issue the remainder of the material, and
> re-close the
> > > job.
> > >
> > > This was present at Vantage 8.03.408B and I believe it still
> > > happens at 9.05.700.
> > >
> > > --- In vantage@yahoogroups.com, Jose Gomez <jose@> wrote:
> > > >
> > > > Hi All
> > > > Here is a fun one,
> > > > We just discovered that ANY Kan Ban job with a production Qty of
> > > > less
> > > than
> > > > 1 but greater than 0 so anything that is a "Partial" unit gets
> issued the
> > > > wrong amount of materials For Example
> > > >
> > > > We have a Mom for Part XXX which requires 2 PPP Parts Per if we
> create a
> > > > Kan Ban job for .5 XXX this is what ends up happening
> > > >
> > > > It correctly calculates a Required Qty of 1 PPP since originally
> > > > it required 2 PPP and we are cutting that in 1/2
> > > >
> > > > But then at Issue time it once again divides the required qty in
> > > > half Issuing only .5 PPP
> > > >
> > > > Has anyone seen this?
> > > >
> > > >
> > > >
> > > > *Jose C Gomez*
> > > > *Software Engineer*
> > > > *
> > > > *
> > > > *
> > > > *T: 904.469.1524 mobile
> > > > E: jose@
> > > > http://www.josecgomez.com
> > > > <http://www.linkedin.com/in/josecgomez> <
> > > http://www.facebook.com/josegomez>
> > > > <http://www.google.com/profiles/jose.gomez> <
> > > http://www.twitter.com/joc85>
> > > > <http://www.josecgomez.com/professional-resume/>
> > > > <http://www.josecgomez.com/feed/> <http://www.usdoingstuff.com>
> > > >
> > > > *Quis custodiet ipsos custodes?*
> > > >
> > > >
> > > > [Non-text portions of this message have been removed]
> > > >
> > >
> > >
> > >
> >
> >
> > [Non-text portions of this message have been removed]
> >
>
>
>


[Non-text portions of this message have been removed]



------------------------------------

Useful links for the Yahoo!Groups Vantage Board are: ( Note: You must have
already linked your email address to a yahoo id to enable access. )
(1) To access the Files Section of our Yahoo!Group for Report Builder and
Crystal Reports and other 'goodies', please goto:
http://groups.yahoo.com/group/vantage/files/.
(2) To search through old msg's goto:
http://groups.yahoo.com/group/vantage/messages
(3) To view links to Vendors that provide Vantage services goto:
http://groups.yahoo.com/group/vantage/linksYahoo! Groups Links
Hi All
Here is a fun one,
We just discovered that ANY Kan Ban job with a production Qty of less than
1 but greater than 0 so anything that is a "Partial" unit gets issued the
wrong amount of materials For Example

We have a Mom for Part XXX which requires 2 PPP Parts Per if we create a
Kan Ban job for .5 XXX this is what ends up happening

It correctly calculates a Required Qty of 1 PPP since originally it
required 2 PPP and we are cutting that in 1/2

But then at Issue time it once again divides the required qty in half
Issuing only .5 PPP

Has anyone seen this?



*Jose C Gomez*
*Software Engineer*
*
*
*
*T: 904.469.1524 mobile
E: jose@...
http://www.josecgomez.com
<http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
<http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
<http://www.josecgomez.com/professional-resume/>
<http://www.josecgomez.com/feed/>
<http://www.usdoingstuff.com>

*Quis custodiet ipsos custodes?*


[Non-text portions of this message have been removed]
Yes, we would regularly complete Kanban Receipts of 0.5 or 0.75. I would have to open the job, issue the remainder of the material, and re-close the job.

This was present at Vantage 8.03.408B and I believe it still happens at 9.05.700.

--- In vantage@yahoogroups.com, Jose Gomez <jose@...> wrote:
>
> Hi All
> Here is a fun one,
> We just discovered that ANY Kan Ban job with a production Qty of less than
> 1 but greater than 0 so anything that is a "Partial" unit gets issued the
> wrong amount of materials For Example
>
> We have a Mom for Part XXX which requires 2 PPP Parts Per if we create a
> Kan Ban job for .5 XXX this is what ends up happening
>
> It correctly calculates a Required Qty of 1 PPP since originally it
> required 2 PPP and we are cutting that in 1/2
>
> But then at Issue time it once again divides the required qty in half
> Issuing only .5 PPP
>
> Has anyone seen this?
>
>
>
> *Jose C Gomez*
> *Software Engineer*
> *
> *
> *
> *T: 904.469.1524 mobile
> E: jose@...
> http://www.josecgomez.com
> <http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
> <http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
> <http://www.josecgomez.com/professional-resume/>
> <http://www.josecgomez.com/feed/>
> <http://www.usdoingstuff.com>
>
> *Quis custodiet ipsos custodes?*
>
>
> [Non-text portions of this message have been removed]
>
Any way to not have the Kaman auto close?
On Apr 11, 2013 5:56 PM, "richard_bacon@..." <rbacon@...>
wrote:

> **
>
>
> Yes, we would regularly complete Kanban Receipts of 0.5 or 0.75. I would
> have to open the job, issue the remainder of the material, and re-close the
> job.
>
> This was present at Vantage 8.03.408B and I believe it still happens at
> 9.05.700.
>
> --- In vantage@yahoogroups.com, Jose Gomez <jose@...> wrote:
> >
> > Hi All
> > Here is a fun one,
> > We just discovered that ANY Kan Ban job with a production Qty of less
> than
> > 1 but greater than 0 so anything that is a "Partial" unit gets issued the
> > wrong amount of materials For Example
> >
> > We have a Mom for Part XXX which requires 2 PPP Parts Per if we create a
> > Kan Ban job for .5 XXX this is what ends up happening
> >
> > It correctly calculates a Required Qty of 1 PPP since originally it
> > required 2 PPP and we are cutting that in 1/2
> >
> > But then at Issue time it once again divides the required qty in half
> > Issuing only .5 PPP
> >
> > Has anyone seen this?
> >
> >
> >
> > *Jose C Gomez*
> > *Software Engineer*
> > *
> > *
> > *
> > *T: 904.469.1524 mobile
> > E: jose@...
> > http://www.josecgomez.com
> > <http://www.linkedin.com/in/josecgomez> <
> http://www.facebook.com/josegomez>
> > <http://www.google.com/profiles/jose.gomez> <
> http://www.twitter.com/joc85>
> > <http://www.josecgomez.com/professional-resume/>
> > <http://www.josecgomez.com/feed/>
> > <http://www.usdoingstuff.com>
> >
> > *Quis custodiet ipsos custodes?*
> >
> >
> > [Non-text portions of this message have been removed]
> >
>
>
>


[Non-text portions of this message have been removed]
Not that I know of, since that's supposed to be one of the benefits of Kanban Receipts (Auto job creation, labor/mtl issuing, and job closing).


--- In vantage@yahoogroups.com, Jose Gomez <jose@...> wrote:
>
> Any way to not have the Kaman auto close?
> On Apr 11, 2013 5:56 PM, "richard_bacon@..." <rbacon@...>
> wrote:
>
> > **
> >
> >
> > Yes, we would regularly complete Kanban Receipts of 0.5 or 0.75. I would
> > have to open the job, issue the remainder of the material, and re-close the
> > job.
> >
> > This was present at Vantage 8.03.408B and I believe it still happens at
> > 9.05.700.
> >
> > --- In vantage@yahoogroups.com, Jose Gomez <jose@> wrote:
> > >
> > > Hi All
> > > Here is a fun one,
> > > We just discovered that ANY Kan Ban job with a production Qty of less
> > than
> > > 1 but greater than 0 so anything that is a "Partial" unit gets issued the
> > > wrong amount of materials For Example
> > >
> > > We have a Mom for Part XXX which requires 2 PPP Parts Per if we create a
> > > Kan Ban job for .5 XXX this is what ends up happening
> > >
> > > It correctly calculates a Required Qty of 1 PPP since originally it
> > > required 2 PPP and we are cutting that in 1/2
> > >
> > > But then at Issue time it once again divides the required qty in half
> > > Issuing only .5 PPP
> > >
> > > Has anyone seen this?
> > >
> > >
> > >
> > > *Jose C Gomez*
> > > *Software Engineer*
> > > *
> > > *
> > > *
> > > *T: 904.469.1524 mobile
> > > E: jose@
> > > http://www.josecgomez.com
> > > <http://www.linkedin.com/in/josecgomez> <
> > http://www.facebook.com/josegomez>
> > > <http://www.google.com/profiles/jose.gomez> <
> > http://www.twitter.com/joc85>
> > > <http://www.josecgomez.com/professional-resume/>
> > > <http://www.josecgomez.com/feed/>
> > > <http://www.usdoingstuff.com>
> > >
> > > *Quis custodiet ipsos custodes?*
> > >
> > >
> > > [Non-text portions of this message have been removed]
> > >
> >
> >
> >
>
>
> [Non-text portions of this message have been removed]
>
So Is spoke to Epicor Serveral times, did a web ex and now they came back
and said. We are able to replicated in all versions all the way through 9.
WTF has no one ever reported this? hahah. So they are gonna fix it, for you
9 people. We lowly 8 people are scrwed! But Cest La Vie!


*Jose C Gomez*
*Software Engineer*
*
*
*
*T: 904.469.1524 mobile
E: jose@...
http://www.josecgomez.com
<http://www.linkedin.com/in/josecgomez> <http://www.facebook.com/josegomez>
<http://www.google.com/profiles/jose.gomez> <http://www.twitter.com/joc85>
<http://www.josecgomez.com/professional-resume/>
<http://www.josecgomez.com/feed/>
<http://www.usdoingstuff.com>

*Quis custodiet ipsos custodes?*


On Thu, Apr 11, 2013 at 6:53 PM, richard_bacon@... <rbacon@...
> wrote:

> **
>
>
> Not that I know of, since that's supposed to be one of the benefits of
> Kanban Receipts (Auto job creation, labor/mtl issuing, and job closing).
>
> --- In vantage@yahoogroups.com, Jose Gomez <jose@...> wrote:
> >
> > Any way to not have the Kaman auto close?
> > On Apr 11, 2013 5:56 PM, "richard_bacon@..." <rbacon@...>
> > wrote:
> >
> > > **
>
> > >
> > >
> > > Yes, we would regularly complete Kanban Receipts of 0.5 or 0.75. I
> would
> > > have to open the job, issue the remainder of the material, and
> re-close the
> > > job.
> > >
> > > This was present at Vantage 8.03.408B and I believe it still happens at
> > > 9.05.700.
> > >
> > > --- In vantage@yahoogroups.com, Jose Gomez <jose@> wrote:
> > > >
> > > > Hi All
> > > > Here is a fun one,
> > > > We just discovered that ANY Kan Ban job with a production Qty of less
> > > than
> > > > 1 but greater than 0 so anything that is a "Partial" unit gets
> issued the
> > > > wrong amount of materials For Example
> > > >
> > > > We have a Mom for Part XXX which requires 2 PPP Parts Per if we
> create a
> > > > Kan Ban job for .5 XXX this is what ends up happening
> > > >
> > > > It correctly calculates a Required Qty of 1 PPP since originally it
> > > > required 2 PPP and we are cutting that in 1/2
> > > >
> > > > But then at Issue time it once again divides the required qty in half
> > > > Issuing only .5 PPP
> > > >
> > > > Has anyone seen this?
> > > >
> > > >
> > > >
> > > > *Jose C Gomez*
> > > > *Software Engineer*
> > > > *
> > > > *
> > > > *
> > > > *T: 904.469.1524 mobile
> > > > E: jose@
> > > > http://www.josecgomez.com
> > > > <http://www.linkedin.com/in/josecgomez> <
> > > http://www.facebook.com/josegomez>
> > > > <http://www.google.com/profiles/jose.gomez> <
> > > http://www.twitter.com/joc85>
> > > > <http://www.josecgomez.com/professional-resume/>
> > > > <http://www.josecgomez.com/feed/>
> > > > <http://www.usdoingstuff.com>
> > > >
> > > > *Quis custodiet ipsos custodes?*
> > > >
> > > >
> > > > [Non-text portions of this message have been removed]
> > > >
> > >
> > >
> > >
> >
> >
> > [Non-text portions of this message have been removed]
> >
>
>
>


[Non-text portions of this message have been removed]