We run MRP and the scheduling module to start the production schedule with the current date.
When we check the overload informer it shows overload hours for various dates in a specific time period of 2018. But shows nothing between there and now.
I have checked all the jobs and operations that were scheduled back then, and they are closed.
We have the same thing going on here. I’ve yet to hear of a user who can make Overload Informer work for them.
Same data affects the imbedded Shop Load graphs. There is a cleanup procedure for the underlying data, but it’s nothing I’ve been able to successfully convince our IT department to address.