Overrun qty - default warehouse

When you create a job, you can take a subassembly and have it pull inventory from a warehouse. In that section where you assign the pull quantity, you can also select the warehouse to pull from. By default, I believe the warehouse that shows up there is the primary warehouse.

My question is, if I were to change that warehouse, would that new warehouse be the location parts would auto receive into if any excess was reported against that subassembly?

For example, if the job was for 10 and they reported 12 pieces, would that part auto receive into into the primary warehouse that is set on the part master or does it auto receive into the new location that was changed on that assembly?

Thanks,

Jasper





[Non-text portions of this message have been removed]